Company: | Leibniz Universität Hannover (LUH), Deutsches Zentrum für Luft- und Raumfahrt (DLR) |
Manager: | Jan Hinzmann |
Start: | December 4, 2006 |
Finish: | June 5, 2007 |
Phase: | execution |
Report Date: | April 17, 2007 |
|
|
WBS | Name | Start | Finish | Work | Priority | Complete | Cost |
---|---|---|---|---|---|---|---|
1 | Startup | Dec 4 | Dec 6 | 8d | |||
1.1 | 06.12.06 Anmeldung | Dec 4 | Dec 6 | 8d | 100% | ||
2 | Theorie | Dec 6 | Jan 17 | 30d | |||
2.1 | Aufbau von Java Interfaces | Dec 6 | Jan 17 | 15d | 100% | ||
2.2 | Identifikation von möglichen Regeln | Dec 6 | Jan 17 | 15d | 70% | ||
3 | Praxis | Jan 17 | Mar 23 | 47d | |||
3.1 | Anforderungsanalyse | Jan 17 | Jan 26 | 7d | 70% | ||
3.2 | Grobdesign | Jan 26 | Feb 2 | 5d | 90% | ||
3.3 | Feindesign | Feb 2 | Feb 9 | 5d | 60% | ||
3.4 | Implementierung | Feb 9 | Mar 23 | 15d | 80% | ||
3.5 | Testen | Feb 9 | Mar 23 | 15d | 80% | ||
4 | Fallstudie | Mar 23 | Apr 6 | 10d | |||
4.1 | Anwendung auf SiLEST | Mar 23 | Apr 6 | 10d | 70% | ||
5 | Bericht | Apr 6 | Jun 1 | 40d | |||
5.1 | Schreiben | Apr 6 | Jun 1 | 40d | 15% | ||
6 | MS4 -ABGABE- | Jun 1 | Jun 4 | 6h | |||
6.1 | Drucken + Binden | Jun 1 | Jun 1 | 5h | 0% | ||
6.2 | Abgeben | Jun 4 | Jun 4 | 1h | 0% | ||
7 | Abgabe 05.06.2007 | Jun 5 | Jun 5 |
Name | Short name | Type | Group | Cost | |
---|---|---|---|---|---|
Axel Berres | Work | Betreuer | 0 | ||
Daniel Lübke | Work | Betreuer | 0 | ||
Jan Hinzmann | Work | MA Arbeiter | 0 | ||
Prof. Kurt Schneider | Work | Prüfer | 0 | ||
Prof. Nicola Henze | Work | Prüfer | 0 |